Author Archives: Giles Parker

Stage 1 – framing up walls and plumbing

The fire rated ceiling has been installed and the plumbing lines dug out and back filled. Hillar is getting ready for the wall linings to begin.

Posted in Renovations | Comments Off on Stage 1 – framing up walls and plumbing

Stage 1 – demolition

Hillar and Arne got to work on the demolition and installation of new concrete lintels ready to start framing the new bathrooms at the entry to Eesti Maja.

Posted in Renovations | Comments Off on Stage 1 – demolition

Archives Office

Februray 2022 The first stage of the upgrade works at Estonian House has been completed. Hillar Ranniko and Arne Rahnel have been busy getting everything ready for the huge task of moving all the books and archive items from upstairs … Continue reading